Calder Casino
Miami Gardens, FL
Mason Contractor:
Central Broward Construction, Inc.
Architect:
JCJ Architecture
General Contractor:
James A. Cummings, Inc.
Suppliers:
Harwood Brick
Owner: Calder Racecourse
Wall System: Cavity Wall: Brick Veneer/Steel Stud
Project Description
Intricately designed with 2 different types of brick veneer and one type of stone. The schedule was very aggressive consisting of after hour, night work, during the holiday season. The casino was closed and was completed in three weeks.
Date of Project Completion: January 2010