A Misunderstanding or a Mortar Failure?

Words: Brian CarneyIn the construction industry, standard specifications and test methods are established to ensure that building materials are properly produced for compliance. However, too often the objective of tests and their results are misinterpreted. Field testing of job site mortar is included in a project specification for pre-construction and construction evaluation only, not to be compared to the performance parameters for a material specification. Unfortunately, in some cases, the end result is an "apples to oranges" comparison in which the final product presumably fails to meet specification.

When the subject is masonry mortars and field testing, pay close attention to the following statement printed by the American Society for Testing and Materials (ASTM): "The test results obtained under the test method (C 780) are not required to meet the minimum compressive strength values in accordance with the property specification in Specification C 270." This statement is found in the Scope of ASTM C 780 Standard Test Method for Pre-construction and Construction Evaluation of Mortars for Plain and Reinforced Unit Masonry (section 1.3). Appropriately, the committee members are assigned to ASTM C 780 have included this comment in the standard's scope to help avoid any possible confusion. There is a simple reason for this assertion.

It should be no surprise that the water content of a given mortar will have a dramatic affect on the specimens compressive strength. Laboratory mortar complying with C 270 is produced with an insufficient amount of water conducive to good field working conditions or fluidity. Mortar made at the job site, which is often tested in accordance to C 780, will have additional mixing water to accommodate the absorption of the masonry unit.

After 28 days of curing, the 2"x4" cylinders cast from construction mortar at a flow (fluidity) greater than 135% will attain only 71% of the compressive strength achieved by the same mixture tested in the lab at 105% flow. In theory, then, if 1800 psi is desired for C 270 Type S mortar, job site mortar should only be expected to attain a strength of 1278 psi.

Construction mortar sampled in the field using ASTM C 780 should not be expected to obtain as high a strength as mortar prepared in the lab using ASTM C 270. This fact is commonly misunderstood which leads to problems. Occasionally, design professionals have shut down projects due to misinterpretation of field test results. Tests conducted under C 780 were intended to evaluate field mixed mortars for consistency and composition, not conformance to property requirements in C 270. Factory pre-blended mortar offers the customer accurately weighed mix designs, and the opportunity to test according to C 270. The proper field testing of pre-blended mortar would involve sampling the dry premixed mortar and running the compressive test under the requirements of C 270.
From Bikes to Buildings: The Importance of Embracing Rainscreen Wall Designs and the New Building Codes.
July 2025

Have you ever been asked to do a project over the course of your lifetime? For example, when my kids were little, my wife asked me to assemble their bicycles. So, I opened the box, dumped out the contents, and cast aside whatever I thought was unnecessary

Laying the Foundation for Growth: Concrete Masonry Checkoff Unveils Five-Year Vision for Industry
July 2025

The Concrete Masonry Checkoff (CMC) put the finishing touches on an ambitious five-year vision for the industry, targeting a 20% increase in market share, driven by increased demand for concrete masonry products. “This is about building exquisite, enduri

Proudly American-Made: EZG Manufacturing’s Commitment to Quality, Innovation, and the U.S. Workforce
July 2025

As supply chain disruptions and tariff concerns continue to impact industries worldwide, EZG Manufacturing remains steadfast in its commitment to providing high-quality, innovative masonry equipment—proudly built in the U.S.A. For 25 years, our Malta, Ohi

Five of the Seven Chimneys Have Been Saved: Project Chimney Update
July 2025

In the wake of the devastating January wildfires that swept through Los Angeles's Pacific Palisades, a remarkable preservation effort is underway, spearheaded by Project Chimney, an initiative led by Evan Hall, founding director of the non-profit House Mu