Crews started stabilization work Friday on a downtown Aurora building that partially collapsed Nov. 11 on the 100 block of East Galena Boulevard, according to city officials.
The city said stabilization and selective demolition are scheduled to run through Nov. 27. After that, the engineering firm overseeing the project plans to inspect the structure. City officials said impacted sections of Galena Boulevard and Broadway are set to reopen after final approval, and the building will be deemed structurally sound once that sign-off is complete.
Aurora Mayor John Laesch told The Beacon-News that the goal is to reopen Broadway by the Monday after Thanksgiving.
The cause of the collapse remains under investigation. John Curley, Aurora’s chief development services officer, said attention has centered on a structural issue involving a truss on the building’s south wall. He estimated the truss and roof structure date back about 175 years. Curley also said the building owner’s insurance structural engineer is investigating whether preparatory work connected to masonry construction played a role in compromising the south wall.
Building owners Harish Ananthapadmanabhan and Jay Punukollu of JH Real Estate Partners said masonry work began Nov. 2. Ananthapadmanabhan said residents received a 30-day notice to vacate before Oct. 31 after the city issued a permit for masonry replacement work. Officials said residents had vacated before the collapse, although some belongings remained inside.
Curley said the repair effort traces back to a 2025 incident when a small section of brick facade fell into the roadway. A private structural engineer later advised the city the building was sound and the brick loss related to a lack of wall ties to the building’s masonry, Curley said. He added that the city does not believe the veneer itself caused the larger failure.
City officials said scaffolding has been restored to create a protective sidewalk canopy, and crews installed construction fencing around the site. The planned work includes interior wall installation, debris removal with heavy equipment, and additional limited removals to support stabilization. Curley said the owner’s structural engineer believes the structure is salvageable, with insurance costs influencing the final outcome.
Read the full, original article from Chicago Tribune (subscription required at source) here.