Historic Brick Matching Drives Denver Museum East Plaza Renovation

2 min read

Historic Brick Matching Drives Denver Museum East Plaza Renovation

2 min read

The Denver Museum of Nature and Science’s renovated East Lobby now features a Milky Way-inspired ceiling installation where each light represents a real star. The work required hand drilling every point and threading individual fiber behind it, and the team adjusted the schedule after flooding in Houston delayed delivery of some components. The project still finished on time and under budget.

Beyond the lobby, the renovation balanced new construction with historic preservation while adding an enhanced entry and an outdoor pavilion connected to City Park. Exterior work restored elements dating to 1939, including the original staircase, and new pavilions were designed as interactive art inspired by Colorado’s seasons.

For mason contractors, the most instructive work happened on the east facade. The facade combined masonry from 1938 and 1939 with an enclosed stairway addition from the 1980s. Removing that vestibule meant rebuilding facade and stair sections that had been hidden for decades. With the original bricks no longer available, the team used museum records to identify the original color, worked with a mason on an initial match, then hand-matched sample after sample until the replacement work blended into the existing wall. The staircase also needed extensive structural repair that was carefully matched to historic concrete work.

Inside, crews uncovered terrazzo flooring from the 1930s that had been damaged by carpet installed over it. A specialty tile subcontractor ground and polished the original material rather than replacing it. When demolition damaged parts of the historic pediment at the east entry, the team captured existing conditions using high-accuracy laser scanning, converted the scans into a 3D model, and used it to generate fabrication and precast shop drawings for replacement components that matched the original architecture.

The team also sequenced work so the theater continued hosting events. New mechanical systems were tied in above the Ancient Egypt Exhibit, and the contractor managed temporary mechanical systems to maintain the temperature requirements while the exhibit stayed open.

Read the full, original article from Engineering News-Record (subscription required at source) here.

About: The Daily Digest
Cornerstone BadgeCORNERSTONE
Amerimix logo CrewTracks logo EZ Scaffold logo EZG Manufacturing logo Hohmann and Barnard, Inc. logo Hydro Mobile Division of Brand Safway Access Inc. logo Ironsite logo PROSOCO, Inc. logo SPEC MIX LLC logo Stabila logo Westlake Royal Stone Solutions logo
Platinum BadgePLATINUM
iQ Power Tools logo Revailo logo Wire-Bond logo