Work has started on a major renovation of the former Union City Chair office building on Market Street in Union City, Pennsylvania, a two-story, 3,200-square-foot brick building tied to the borough’s furniture-making history.
The building, constructed in the 1907-1911 time frame, sits next to the former Union City Chair manufacturing site along the South Branch of French Creek. After the office building and a rear retail-sales building were split from the main property and sold in 2021, the office structure continued to deteriorate, including ongoing roof leaks and growing concern about the stability of the rear brick wall.
In recent years, McLane Baptist Church sought help to address the building’s condition. The Erie County Land Bank pursued a state Local Share Account grant for $103,500 to stabilize the back wall and install a new roof and windows to secure the exterior envelope. The Land Bank later opted not to take on the project, and the Erie County Redevelopment Authority stepped in to take ownership and responsibility for the grant.
The funding picture then improved significantly. Along with the $103,500 state grant, the Redevelopment Authority still had about $118,000 in county funds previously awarded to Union City for such a project, and the county added $330,000 earlier this year, bringing total funding for the project to $551,500. The Redevelopment Authority is holding about $96,500 in reserve for administrative costs, architectural fees, and permitting, leaving $454,500 initially available for construction work.
Bids totaling $331,164 were awarded for exterior restoration and limited interior improvements. The scope includes selective demolition and stabilization, roof replacement and structural repairs, foundation repairs and restoration, and masonry repairs. It also includes window replacement and concrete trim restoration, exterior door modifications to provide a second exit, cornice restoration and painting, and limited floor repairs tied to water damage. Separate bids cover heating units with air handlers, electrical service rerouting from overhead to underground, and replacement of the front sidewalk.
For crews involved in brick building restoration, the project’s sequencing highlights a familiar reality: stabilizing masonry and stopping water intrusion drives the rest of the scope, schedule, and cost.