Case Study: The Revere Condominiums at River Oaks

Words: Kevin Camarata
Photos: Camarata Masonry Systems

The Revere is a boutique condominium located in the River Oaks area of Houston. The nine-story development offers 33 residences with refined amenities for those looking for luxury living near the downtown area.

Material Selection And Facade Details
The veneer of this rectangular-shaped mid-rise building is primarily comprised of oversized burnished block measuring 16 by 24 inches. A utility brick is utilized on the south elevation with pilasters of burnished units protruding from the field. Cast stone banding is used throughout the upper floors, on the coping, and on the landscaping planters.

The facade utilizes many rustications, including picture framing, recesses, angled pieces, and chamfers, which create a high-end appearance.

  

Tight Quarters And Hoisting Challenges
From the beginning, Camarata Masonry Systems, Ltd. (CMS) knew this project was going to be challenging. The footprint of the building is only 5 feet away from the property lines on the south and east elevations, with an adjacent townhouse built on the edge of the east property line. The north and west elevations are built within 16 feet of the edges of the roads, and the west side electrical lines are within 7 feet of the finished building.

A small amount of storage inside the two-story parking garage was available, but due to the extremely tight site conditions, the primary laydown area was located two blocks away. The site conditions were analyzed in the pre-planning stage, with particular attention paid to hoisting. The crane could not be utilized for the entire duration; therefore, a prioritized buck-hoist was necessary to service the building.



Navigating The Scaffolding
Several types of scaffolding were used due to the structure’s proximity to adjacent property. Conventional welded tubular frame scaffolding and multi-point suspended swing stages encapsulated the building. In order for the roof installation to continue uninterrupted, CMS installed the masonry veneer cladding at the parapet utilizing welded tubular frame scaffolding supported by outrigger beams laid out on the floor deck and extended out through the exterior walls at the eighth floor. Lightweight swing stages were then used to patch outrigger beam holes after the work on the roof was complete.

Distribution was difficult on the south elevation as the 5 feet between the building and the masonry fence on the property line created a “tunnel.” The veneer work on this side involved working on or over the property line with great care taken to prevent loose materials from falling into the open parking courtyard below.

The east elevation’s proximity to the adjacent townhouses presented additional challenges, especially with the work on the project encroaching into the 5-foot space on the first floor and cantilevering over 2 feet into that space at the third floor and above. Because of the narrow space on this side, 3-foot welded tubular frame scaffolding was used while working at the same level as the adjacent building, and an agreement was made for us to enter the townhouse’s air space so we could use our multi-point suspended scaffold system above their roof.

 

Streamlining The Block Shapes
A unique feature of the project is the use of oversized burnished block units. Originally, 49 different shapes were specified. Knowing that site storage space and logistics were going to be major issues and that the supplier’s schedule would be unduly lengthened by the sheer number of shapes, the project team decided to reduce the 49 shapes to a more manageable 22 shapes.

This was achieved by mapping out each piece of burnished block on the entire building and identifying where each shape was to be used. Multiple meetings with the supplier were held to identify which shapes and angles would work best for the new plan and which could be field-fabricated. After these meetings, the drawings were re-mapped to specify where the 22 shapes would be used, and directions were developed on how to field-fabricate the additional 27 shapes from the 22 standard shapes.

Planning was important to ensure the modified shapes would be created and installed efficiently. To help this process, a saw and a mixing station were set up on every floor, including the roof, as work progressed up the building.

   

Final Thoughts
The project was completed on time and within budget while working in extremely difficult conditions with no recordable or lost-time accidents. The detailed burnished block installation combined with the brick veneer resulted in a building facade that exemplifies the craftsmanship and proficiency of our masons.


About: Case Study
URGENT: Only One Cornerstone Spot Remains in the 2026 Masonry Alliance Program
May 2026

The Mason Contractors Association of America (MCAA) is thrilled to announce that the 2026 Masonry Alliance Program (MAP) has reached a critical stage of exclusivity.

The Compliance Shield: Navigating the New Standards of Field Oversight
May 2026

The modern job site is undergoing a quiet but significant transformation. While the physical act of laying a block remains the core of the trade, the environment surrounding that work is becoming increasingly data-driven. We are moving away from the era o

When GEORGE Met BOB: Ironsite Is MCAA's First AI-Centered Cornerstone Partner
May 2026

Earlier this year at World of Concrete, I taught the AI Test Drive class and gave attendees an early look at GEORGE 3.0, which we're set to release later this year. As I was wrapping up the session and people were still asking questions, the team from Iro

Ironsite Joins Masonry Alliance Program as Newest Cornerstone Partner
May 2026

The Mason Contractors Association of America (MCAA) is thrilled to announce that Ironsite will be joining the Masonry Alliance Program (MAP) at the Cornerstone level.