Cavity Wall: Concrete Block Veneer/Reinforced Cast in Place Concrete

The excellent insulating value and heat capacity of masonry and concrete make this system a good choice for schools and commercial buildings.

Cavity Wall: Concrete Block Veneer/Reinforced Cast in Place Concrete
Coping and dove-tail anchor wall ties Relieving angle and flashing at opening

Recommended Building Types

Benefits

  • Durable, long-lasting wall system
  • Minimal long-term maintenance
  • Great design flexibility – use different colors, bond patterns, and surface textures to spice up your design
  • Poured concrete backup acts as the structure, with vertical and horizontal reinforcement built into the wall
  • Cavity system inherently weatherproof – great for moist environments
  • Excellent insulating value and heat capacity
  • Inherently fire proof with fire rating of 4 hours
  • Great for noisy environments – naturally dampens sound

Special Considerations

  • Lower life cycle costs offset high initial investment
  • This substantial wall system may require larger foundations
  • Two trades required for construction – masonry contractor for the façade, and a concrete contractor for the backup – which can complicate jobsite coordination
  • Construction times are longer than for an equivalent masonry (brick/block) wall
  • Cast-in-place concrete is not a desirable interior finish. Will need to provide final finished surfaces after wall is built

Definition and Assumptions

Backup: Reinforced 8" thick concrete wall. #5 reinforcement at 12 inches o.c. each direction, 2 mats of steel

9-gauge triangular ties in dovetail slots embedded in concrete. Install the dovetail slots vertically @ 24" o.c. Install ties in the slots @ 16" o.c.

Veneer: Cored modular brick 4" x 2-13" x 8" (nom.).

Insulation: 2 inch extruded polystyrene rigid insulation in 3 inch drainage cavity.

flashing: Base flashing and weeps.

Mortar: Type N, Portland cement/lime, plain gray.

Joints: Concave tooled.

Regional Variations

  • When masonry veneer is used in areas of high seismic risk, veneer ties are required to attach to wire reinforcement embedded in mortar bed joints in the veneer. Check your local requirements – and save money by using normal veneer ties in areas of low seismic risk.
  • Many areas of the western U.S. have good local sources for lightweight aggregate, and the use of lightweight concrete block (CMU) is the norm. In other parts of the country, medium weight and normal weight block are more common.

Fire Rating (hours)

4 hours

Sound Transmission Class (dB)

STC 62.7

STC=(weight of wall)0.223x21.5

Wall Weight (lb/sq. ft.)

122 lb/sq. ft.

Energy Rating

R-value: 11.89 with 2” expanded polystyrene rigid insulation (See note)

Calculation:

Outside Air =0.17
4 inch block =1.19
Air Gap =0.97
Insulation =8.00
Gyp board =0.45
8 inch concrete =0.88
Interior Air =0.68
Total =11.89

R-value: 13.89 with 2” extruded polystyrene rigid insulation (See note)

Calculation:

Outside Air =0.17
4 inch block =1.19
Air Gap =0.97
Insulation =10.00
8 inch concrete =0.88
Interior Air =0.68
Total =13.89

Note: The type of rigid insulation you install affects the wall’s insulating capacity (the R-value). Polyisocyanurate insulation gives you 8.0 R per inch (12.0 R for 1.5" or R16 for 2"). Expanded polystyrene insulation is worth 4.0 R per inch (6.0 R for 1.5" or 8 R for 2"). Extruded polystyrene yields 5.0 R per inch (7.5 R for 1.5" or 10 R for 2"). Use either thicker insulation or more expensive polyisocyanurate to achieve a higher energy rating.

Green/LEED Rating

Design Tips

  • Place rigid-board insulation in the drainage cavity to maximize interior usable space, and take advantage of the huge thermal mass provided by the concrete backup system.
  • Concrete block (CMU) veneer shrinks as it ages. Don’t forget to detail expansion joints in the CMU veneer and concrete backup.
  • Install horizontal reinforcing in the concrete block veneer @ 16 inches o.c. to control cracking.
  • Shelf angles may not be required for veneer support at every floor line. Cut down on the number of shelf angles to save money and simplify your construction. If your veneer is shorter than 30 feet above the top of the foundation wall, you may not need relieving angles at all.

Construction Tips

  • Back bevel mortar joints to prevent excess mortar from falling into the drainage cavity.
  • Dovetail slots are expensive for the concrete contractor to install and are often left out. You may need to face-mount dovetail slots using anchors installed into the concrete.
The Importance of Instructor Support
April 2026

Whether you are a new or veteran masonry instructor, we all need support throughout our careers. We can never stop learning, and keeping up with ever-changing technology, materials, and installation techniques can be overwhelming alongside the everyday pr

Vibing Masonry #11: Innovative Concrete Masonry Technologies in Healthcare Design
April 2026

In the high-stakes environment of healthcare design, every material choice is a clinical decision. Architects, engineers, and facility administrators are tasked with creating spaces that are not only resilient and code-compliant but also conducive to heal

Why Termination Bars Still Matter: A Practical Look at Long‑Term Flashing Performance
April 2026

In recent discussions across the masonry industry, I have heard termination bars described as “old school.” The implication is that with modern materials, primerless peel-and-stick flashings, advanced sealants, and structural insulated sheathing, mechanic

Building Solutions: The Critical Role of Cavity Space in Masonry Moisture Control
April 2026

Long before “rainscreen” became a popular term in building science, masonry cavity walls were functioning on that very principle. A brick veneer cavity wall is designed with the expectation that water will penetrate the exterior